Use linear extrapolation to estimate total units completed at 6:00 P.M.
Table of data 4:07 P.M. 14371 1
5:01 P.M. 16110 2
6:00 P.M. 99979 p
You can use the equations given for interpolation for extrapolation.
![15144|409x166](upload://3PBK0CZvwQE1DRgusnZQlJjPVVh.jpeg)
Total production at 6:00 P.M. is estimated to be 18010 units,
Check by units per minute:
Between 5:01 P.M. and 4:07 P.M. (54 minutes)
Units grow by (16110 — 14371) or 1739 units. Thus, units per minute are 1739 / 54 = 32.2037 (units/min) 6:00 P.M. is 113 minutes after 4:07 P.M.,
Thus, production at 6:00 P.M. = 32.2037 (units/min) * 113 (min)
This equals 3639 units more then at 4:07 P.M.
Therefore, at 6:00 P.M. the total units are
14371 + 3639 = 18010
You might also like to view...
You can use the attribute value _parent with the target attribute when you want a link to break out of:
A) the noframes element. B) a single frame. C) inline frames. D) nested frames.
Java provides Sphere and Box classes.
Answer the following statement true (T) or false (F)