Using the information in Table J.17 and Johnson's rule, develop a schedule that minimizes makespan for these seven jobs
Assume that job C could be neatly split into two equal parts, each having half of the processing time on each machine as the full job C. Using your original sequence, but splitting job C, what is the makespan for the seven jobs?
A) between 58 and 59 days
B) between 56 and 57 days
C) between 55 and 56 days
D) between 57 and 58 days
D