The first phase of the systems development life cycle (SDLC) is ________

A) defining the system
B) implementing the system
C) determining the requirements
D) maintaining the system

A

Business

You might also like to view...

Advantages of SWOT include each of the following except

A) very simple to use. B) creates an awareness of political and environmental threats. C) encourages customers to provide routine feedback. D) allows the project manager to prepare appropriate response plans.

Business

Float is best described by which of the below?

A) the time that is required to receive payment on a zero balance account B) the term used to describe payment for the purchase of raw materials that are needed to complete production of a luxury liner C) investing excess cash balances D) the time required for a deposited check to clear through the commercial banking system and be available for payment