What is the cost to finish this project (all activity durations are in weeks and costs in US dollars) as quickly as possible?

Activity Predecessor Normal Time Minimum Time Normal Cost Crash Cost
A 12 10 1000 1500
B A 5 3 1200 1950
C A 9 7 1500 2100
D B, C 14 10 1800 2100
E B 4 3 1400 1875
F D 9 8 1000 1450
G E 7 5 700 1200
H F, G 11 8 2000 3000
I H 8 6 1100 1700

The initial project duration is 63 weeks thanks to the valuable contributions of path ACDFHI. Path ABEGHI is 47 weeks and path ABDFHI is 59 weeks long. The base project cost is $11,700.
Purchases from least expensive to most expensive are as follows:
Activity D reduced 4 days for $300
Activity A reduced 2 days for $500
Activity C reduced 2 days for $600
Activity I reduced 2 days for $600
Activity H reduced 3 days for $1,000
Activity F reduced 1 day for $450
The new project length is 49 days with path lengths of ACDFHI=49; ABEGHI=40; and ABDFHI=45. The total project cost is now $15,150.

Business

You might also like to view...

Some research suggests that advertising and MPR

A) are incompatible marketing techniques. B) both require enormous financial investment to be successful. C) help increase short-term sales but remain ineffective in the long-run. D) stimulate growth in newspaper readership. E) are equally effective techniques for building product awareness.

Business

Which of the following will interfere with access to operational databases?

A) Unstructured and unpredictable use of data B) Predictable use of data C) Efficient transaction processing systems D) All of the above

Business