Calculate the average lateness using the earliest due date criterion to determine the schedule for these five jobs
Job Process Time Due Date
A 2 7
B 8 16
C 4 4
D 10 17
E 5 15
A) 3
B) 10
C) 12.4
D) 14
Answer: A