A project has the activity duration and cost information indicated in the table where all times are in weeks

What is the total cost for completing this project in 40 days?

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
A -- 8 $12,000 5 $22,000
B A 12 $18,000 9 $32,000
C A 15 $22,000 9 $62,000
D B 3 $9,000 2 $18,000
E C 9 $15,000 5 $35,000
F E 7 $5,000 5 $8,000
G D 8 $13,000 6 $23,000
H A 12 $20,000 8 $32,000
J H 6 $45,000 4 $56,000
A) $172,000
B) $218,000
C) $192,000
D) $159,000

A