Outputs of the Plan Risk Responses process include:
A. Secondary risks, process updates, and risk owners.
B. Risk triggers, contracts, and a risk list.
C. Residual risks, fallback plans, and contingency reserves.
D. Contingency plans, project management plan updates, and a sensitivity analysis.
Answer: C. Residual risks, fallback plans, and contingency reserves.