The overall project risk factor is known to be 0.5. The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure

The consequence of performance failure is twice the consequence of reliability failure, four times the consequence of schedule failure and eight times the consequence of cost failure. What is the difference between the probability of maturity failure and the consequence of cost failure?

Maturity X Cost Y
Complexity 2X Schedule 2Y
Dependency 4X Reliability 4Y
Performance 8Y
A) 0.026
B) 0.033
C) 0.041
D) 0.048

A

Business

You might also like to view...

Michelle has a term insurance policy in which the amount of protection remains constant during the term period. Which kind of term insurance does Michelle have?

A) Level term B) Increasing term C) Family term D) Decreasing term"

Business

Which of the following organizational structures will be suited for a company that sells business to business products?

A) market-based structure B) product-focused structure C) classic brand structure D) internationally focused structure

Business