The process of smoothing out the utilization of resources in a project is called

A) CPM.
B) PERT.
C) project crashing.
D) work breakdown structure.
E) resource leveling.

E

Business

You might also like to view...

In business presentations, the backchannel is

A) the "notes" portion of an electronic slide, which only the presenter can see. B) subtle, nonverbal cues the presenter sends during the presentation. C) electronic communication among audience members during the presentation. D) password-protected slides that only certain audience members can see. E) an impromptu speech designed to take control of a presentation.