Name five conditions under which a task becomes critical.
What will be an ideal response?
1. The task has 0 slack.
2. The task has a Must Start On or Must Finish On date constraint.
3. The task has an As Late As Possible constraint in a project scheduled from a Start date.
4. The task has an As Soon As Possible constraint in a project scheduled from a Finish date.
5. The task has a scheduled Finish date that is the same or beyond its deadline date. (A deadline date doesn't constrain a task, but it does provide a visual indicator if a scheduled Finish date slips beyond the deadline date.)