Which of the following statements best describes a full-interruption test of the DRP?
A. Members of key departments perform a dry run of the emergency.
B. Members of key departments trace their steps through the plan checking for omissions and inaccuracies.
C. Members of key departments check off the tasks for which they are responsible.
D. Backup processing run simultaneously with the production services.
E. Production systems are stopped to evaluate how backup systems perform.
Answer: E
Explanation: A full interruption test is known as a true/false test and involves stopping the production systems to see how the backup works in case of a disaster.