Which statement about critical chain methodology is BEST?

A) Activity durations estimated at a 50% level of successful completion are shorter than those estimated at a 90% level of successful completion.
B) Aggregated activity durations at a 90% level of successful completion are shorter than aggregated activity durations at a 50% level of successful completion.
C) The total safety buffer for aggregated activity durations is smaller than the sum of safety buffers for individual activity durations at any likely level estimate.
D) None of these statements is correct.

Answer: C) The total safety buffer for aggregated activity durations is smaller than the sum of safety buffers for individual activity durations at any likely level estimate.

Business

You might also like to view...

________ is the examination of frequencies for two categorical variables in a cross-tabulation table to determine whether the variables have a significant relationship

A) Chi-square analysis B) Correlation C) ANOVA D) Regression E) MANOVA

Business

List and describe the three basic socialization responses and tell under what conditions each may be appropriate

What will be an ideal response?

Business