Refer to the figure. What is the earliest start time (EST) and earliest finish time (EFT) of activity E?

A) EST = 7, EFT = 10
B) EST = 10, EFT = 7
C) EST = 11, EFT = 8
D) EST = 8, EFT = 10
E) EST = 8, EFT = 11

E