Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time

Activity Immediate
Predecessor(s) Time
(Weeks)
A --- 3
B --- 4
C A 6
D B 9
E B 6
F C, D 6
G D, E 8
H G, F 9

Activity Earliest
Start Earliest
Finish Latest
Start Latest Finish Slack
A
B
C
D
E
F
G
H

Activity Earliest
Start Earliest
Finish Latest
Start Latest Finish Slack
A 0 3 6 9 6
B 0 4 0 4 0
C 3 9 9 15 6
D 4 13 4 13 0
E 4 10 7 13 3
F 13 19 15 21 2
G 13 21 13 21 0
H 21 30 21 30 0

Critical path is B—D—G—H, and project completion time is 30 weeks.

Business

You might also like to view...

Refer to the scenario above. What is the slack for activity G?

A) 4 weeks. B) 3 weeks. C) 2 weeks. D) 1 week.

Business

Which of the following forms of business organization has the greatest ability to attract new

capital? A) sole proprietorship B) general partnership C) limited partnership D) corporation

Business