A project is composed of the seven activities shown in the table where all activities are in weeks
Activity Activity time Resource Usage Predecessor
J 10 90
F 16 144 I
P 18 180 J, F
I 8 128
N 14 196 I
T 10 220 P, N
O 8 80 P, N
The resource profile for an early start schedule is plotted below.
Suppose that the line representing resource usage is a function of time and is described by the equation Usage=f(t). What is the definite integral of this function over the domain 0 to 52? In other words, find the solution to: for this project.
Mercifully, there's nothing to integrate here. The area under the curve is the total usage of resources for the project, which is the sum of that column in the table. The total is 1038.
You might also like to view...
Which of the following approaches to collecting data is the most flexible?
A) personal interviews B) telephone interviews C) mail D) Internet
Which is least likely to be a reason for the confused state of the leadership literature?
A) the reliance on weak methods for much of the research B) the narrow focus of most empirical studies on leadership C) the use of complex theories to explain leader influence D) a proliferation of confusing terms and diverse definitions