Who is responsible for developing a risk management strategy?

a. A risk reviewer
b. A technical resource
c. A project champion
d. A risk owner

d. A risk owner
Risks with a high probability of occurrence and a high potentialimpact need to have a risk owner assigned. The risk owner is responsible for developing a risk management strategy and monitoring the project to determine if the risk is about to occur or has occurred.

Computer Science & Information Technology

You might also like to view...

To ________ data is to list data in a specific sequence, such as alphabetically or in numeric order

A) label B) key C) group D) sort

Computer Science & Information Technology

Adapt the central server algorithm for mutual exclusion to handle the crash failure of any client (in any state), assuming that the server is correct and given a reliable failure detector. Comment on whether the resultant system is fault tolerant. What would happen if a client that possesses the token is wrongly suspected to have failed?

What will be an ideal response?

Computer Science & Information Technology