Who is responsible for developing a risk management strategy?
a. A risk reviewer
b. A technical resource
c. A project champion
d. A risk owner
d. A risk owner
Risks with a high probability of occurrence and a high potentialimpact need to have a risk owner assigned. The risk owner is responsible for developing a risk management strategy and monitoring the project to determine if the risk is about to occur or has occurred.
You might also like to view...
To ________ data is to list data in a specific sequence, such as alphabetically or in numeric order
A) label B) key C) group D) sort
Adapt the central server algorithm for mutual exclusion to handle the crash failure of any client (in any state), assuming that the server is correct and given a reliable failure detector. Comment on whether the resultant system is fault tolerant. What would happen if a client that possesses the token is wrongly suspected to have failed?