A project consisting of six activities is represented in the resource loading table shown below. There is a limit of 12 hours' time spent on this project for any given day

What activities are involved in the first resource problem in this schedule?

Act. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A 4 4 4 4
B 4 4 4 4 4 4 4 4 4 4 4
C 5 5 5 5 5
D 4 4 4 4 4 4
E 4 4 4 4 4 4
F 6 6 6
A) Activities A, B, and C
B) Activities B, C, and D
C) Activities C, D, and E
D) Activities D, E, and F

D

Business

You might also like to view...

If a business produces 800,000 units and the market demand for the product is 4 million units, what is its percentage of market share?

A) 8% B) 20% C) 16% D) 40% E) 80%

Business

When using social media to talk about topics related to your business, how can you make the information valuable to the audience?

A) Make the posting casual and conversational B) Make the information useful and interesting C) Use only original content D) Use the site for self-promotion and to emphasize the sale of products and services E) Include links to other social media sites

Business