What is hierarchy among the deliverable, work package, subdeliverable, and project? Create an example starting with the most macro element, cascading through to the lowest element
What will be an ideal response?
The highest (most macro) level is the project, followed by in increasing order of specificity, the deliverables, subdeliverables, and work packages. Examples will vary.