Given the following information for a project, identify the critical path and determine the total completion time of the project
Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5
Answer: Critical path = BCEH. Project completion time = 25 days.
Activity ES EF LS LF Slack CP
A 0 6 2 8 2 No
B 0 8 0 8 0 Yes
C 8 13 8 13 0 Yes
D 8 12 10 14 2 No
E 13 20 13 20 0 Yes
F 13 16 17 20 4 No
G 12 18 14 20 2 No
H 20 25 20 25 0 Yes
CP = Critical Path
You might also like to view...
Which of the following is true of Abraham Maslow’s contribution to the field of human relations?
A. He emphasized the maintenance of inventories to meet consumer demand. B. He was concerned with meeting the explosive growth in demand brought about by the industrial revolution. C. He suggested that humans have five levels of needs. D. He concluded that management decisions were unsystematic. E. He advocated the application of scientific methods to analyze work.
The goal of ________ is to observe current practices of the firm, to assess those practices, and to identify gaps in deployment
A) the integrative approach B) information systems C) benchmarking D) organizational learning and knowledge E) self-assessment