Answer the following statements true (T) or false (F)

1. The length of the arrows in a PERT diagram has a direct relationship with the duration of the activity.
2. The critical path is defined as the most expensive path.
3. PERT diagrams occasionally need to use dummy activities to preserve the logic.
4. An advantage of PERT diagrams is the easy determination of slack time.
5. A PERT diagram does not allow for easy identification of the critical path and thus critical activities.

1. FALSE
2. FALSE
3. TRUE
4. TRUE
5. FALSE

Computer Science & Information Technology

You might also like to view...

To enter a name on a sheet tab, ________-click the sheet tab, click Rename on the shortcut menu, and type the sheet name

Fill in the blank(s) with correct word

Computer Science & Information Technology

The choice of which sorting algorithm to use does not affect:

a. How sorted the vector will be. b. The time it takes for the sorting operation to complete. c. The amount of memory used by the program. d. All of the above will be affected by the choice of sorting algorithm.

Computer Science & Information Technology