If significant deviations from the project plan are detected, corrective action is taken and then:
A) The monitoring and control cycle begins anew.
B) Project goals are adjusted to reflect current reality.
C) The project stakeholders are informed of the budget or time difficulties.
D) The critical chain is reviewed for task dependency.
A