Use the project information in the table to resolve resource conflicts, identify the critical chain and critical path, and create feeder buffers
A feeder buffer should be placed immediately before:
Activity Predecessor Length Resource Activity Predecessor Length Resource
A -- 11 P D C 13 P
B A 7 M E -- 12 X
C B 8 W F E 14 M
A) Activity B.
B) Activity F.
C) Activity C.
D) Activity A.
B