A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity
What are the duration and the early start time associated with this hammock activity?
Time Predecessor
A 7
B 8 A
C 13 B
D 8 C
E 7 A
F 6 E
G 6 A
H 11 G
I 12 H
J 14 D, F, I
A) 13, 36
B) 7, 0
C) 13, 7
D) 7, 14
C