With effort-driven scheduling, Project 2013 calculates work using the following formula ________

A) Work (W) = Duration (D) * Units (U) B) Units (U) = Duration (D) / Work (W)
C) Units (U) = Duration (D) * Work (W) D) Duration (D) = Units (U) * Work (W)

A