A manager wants to build 3-sigma x-bar control limits for a process. The target value for the mean of the process is 10 units, and the standard deviation of the process is 6

If samples of size 9 are to be taken, what will be the upper and lower control limits, respectively?
A) -8 and 28
B) 16 and 4
C) 12 and 8
D) 4 and 16
E) 8 and 12

B

Business

You might also like to view...

A set of priority planning techniques for planning component items below the end item level is

called: A) capacity planning. B) material requirements planning. C) master scheduling. D) production control. E) none of the above

Business

Customer/product relationship is an example of

A) one-to-many relationship. B) difficult relationship. C) one-to-one relationship. D) many-to-many relationship.

Business