What is the optimal value of the objective function?

Given the nonlinear programming model:

Max Z = 5x1 - 2x22
Subject to: x1 + x2 = 6

A) Z = 19.625
B) Z = 20.625
C) Z = 21.625
D) Z = 22.625
E) Z = 23.625

Answer: B