Given the forecast and booked orders shown in the table, and a beginning inventory of 25, what is the master production schedule quantity for period 4?
Period 1 2 3 4
Forecasted Demand 70 65 60 55
Booked Orders 80 50 30 10
Projected ending inventory
Master production schedule 55
Available to Promise 0
A) 35
B) 40
C) 55
D) 70
Answer: C
You might also like to view...
An auditor identified a material weakness in internal control in December. The client was informed and the client corrected the material weakness shortly after year-end (December 31); the auditor agrees that the correction eliminates the material weakness as of January 31. The appropriate audit report on internal control under PCAOB standards on reporting on internal control is: