Describe the process of building a risk table.
What will be an ideal response?
Project teams begin by listing all risks. Each risk is categorized by type and its probability is estimated. The impact value of each risk is assessed. Risk probability and impact are used to sort the table. Risks are then classified as high impact or low impact by defining a "cutoff" line. High impact risks (those above the line) receive management attention.