A production line is to be designed for a job with four tasks. The task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes

After line balancing, the largest possible assigned cycle time is ________ minutes, and the smallest possible assigned cycle time is ________ minutes.
A) 1.8; 1.4
B) 1.6; 0.9
C) 6.4; 2.4
D) 2.4; 0.9
E) 6.4; 0.9

C

Business

You might also like to view...

An "integrated audit" includes

A) A special audit related to management fraud. B) A financial statement audit and an audit of internal control over financial reporting. C) A financial statement audit and a special audit related to management fraud. D) A special audit related to management fraud and an audit of internal control over financial reporting.

Business

With the increase in the use of social media, it is important to ________ those who don't follow the rules of ethical communication

A) limit website access from B) not respond to C) diligently guard and defend against D) identify corporate policy for E) hide unhappy customers and their potential for damage away from

Business