Reducing the overall activity time is based on which of the following steps?

A) crashing activities with the lowest overall crash cost
B) crashing activities with the lowest overall normal cost
C) crashing activities on the critical path based on lowest overall cost
D) crashing activities on the critical path based on lowest cost/week
E) crashing activities with the lowest cost/week

D