With a batch size of 300 units, what is the capacity of process A as shown in Scenario 6.1?

A) 10.3 units per hour
B) 11.5 units per hour
C) 12.7 units per hour
D) 13.9 units per hour

A

Business

You might also like to view...

Thermostats are subjected to rigorous testing before they are shipped to air conditioning technicians around the world. Results from the last five samples are shown in the table. Is the process under control?

Unit # Sample 1 Sample 2 Sample 3 Sample 4 Sample 5 1 73.5 70.8 72.2 73.6 71.0 2 71.3 71.0 73.1 72.7 72.2 3 70.0 72.6 71.9 72.4 73.3 4 71.1 70.6 70.3 74.2 73.6 5 70.8 70.7 70.7 73.5 71.1