What is the slack time for activity E?

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38
A) 0 days
B) 1 day
C) 2 days
D) 4 days

A