Manny Manufacturer agreed to buy widgets from Supplier only on the condition that the widgets would be delivered in 10 days time. When Supplier could not meet the delivery date, Manny agreed to accept the widgets one week later. Manny's acceptance of a different performance date under this contract is a(n) _________________of the original condition
a. Repudiation
b. Revocation
c. Waiver
d. Withdrawal
Ans: c. Waiver