Answer the following statements true (T) or false (F)
1. A commitment from management to conduct a feasibility study means that the proposed system is accepted.
2. Using a weighted average formula to determine expected activity times is the best strategy for estimating time.
3. PERT diagrams are useful when activities can be done in parallel rather than in sequence.
4. PERT is an acronym for Program Evaluation and Review Technique.
5. The main advantage of the PERT diagram is its simplicity.
1. FALSE
2. FALSE
3. TRUE
4. TRUE
5. FALSE