Case-Based Critical Thinking QuestionsCase 5-1Diane's boss has asked her to create some interim plans as their newest project progresses, to keep an eye on slippage as they proceed. She has never worked with interim plans before, so she has some questions for you.While she was using one of her interim reports, Diane identified a task that had fallen far behind schedule and that needed to be rescheduled. You tell her that there are a variety of options related to rescheduling work in the Options dialog box. Which of the following is NOT an option to which you alert her?

A. You can use resource status to update the status of tasks.
B. You can determine Earned Value options.
C. You can move the end of completed parts after the status date back to the status date.
D. You can move the start of remaining parts before the status date forward to the status date.

Answer: A

Computer Science & Information Technology

You might also like to view...

To insert an equation, you would first go to the ________ group on the Insert tab

A) Illustrations B) Symbols C) Apps D) Links

Computer Science & Information Technology

The Review your update history page displays all updates that have been installed on your computer

Indicate whether the statement is true or false

Computer Science & Information Technology