Craft Construction entered into a contract to construct a generator station for a utility customer. The project was started in 2016 and completed in 2017. Cost and other information is presented below

2016
2017
Costs incurred during the year
$225,000
$550,000
Estimated costs to complete
450,000
-0-
Billings during the year
200,000
700,000
Cash collections during the year
150,000
750,000
Refer to Craft Construction. Assume Craft uses the percentage-of-completion method for revenue recognition. Compute the amount of gross profit for 2016 and 2017.

What will be an ideal response?

Answer:
2016

Contract price
$900,000

Actual costs to date
225,000

Estimated costs to complete
450,000

Total estimated project costs
675,000

Estimated total gross profit
225,000

Percentage of Completion 225/675
33.33%

Gross profit
$75,000

2017

Contract price

$900,000

Costs Incurred 2016
$225,000

2017
550,000

Total Cost

$775,000

Total Gross Profit

125,000

Recognized in 2016

75,000

Recognized in 2017

50,000

Business

You might also like to view...

According to the Keown book, ________of U.S. households have no life insurance coverage.

A) 15 percent B) 30 percent C) 50 percent D) 65 percent

Business

The ________ theory of ethics is best exemplified by the utilitarian school of thought

A) humanist B) deontological C) consequential D) relativist

Business