A project consists of four activities with information as shown in the table. What is the overall variance of the project's duration?
Activity Predecessor Length Standard Deviation
A -- 10 2
B A 12 3
C A 16 2
D B, C 14 3
A) 13
B) 17
C) 26
D) 35
B