What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 5 --
B 7 --
C 8 A
D 7 A
E 4 B
F 8 C, D
G 9 E, F
H 7 G

A) 15
B) 17
C) 19
D) 21

D