An item sells at a rate of 600 units per day. If a plant works two shifts per day (480 minutes each shift), what takt time is required for the plant to meet this demand?

What will be an ideal response?

480 minutes per shift × 2 shifts = 960 minutes per day
960 minutes per day ÷ 600 units = 1.6 minutes per unit, or 96 seconds per unit