Match each term below to its corresponding phrase. 1. Lead 2. Lag
A. The amount of time required between two dependent tasks
B. The amount of time required to complete two independent tasks
C. The overlap between two assigned tasks that are dependent upon each other
1. = C. The overlap between two assigned tasks that are dependent upon each other
2.=A. The amount of time required between two dependent tasks