Discuss the primary benefit in three-point duration estimating.
What will be an ideal response?
The primary answer is the use of optimistic, pessimistic, and most likely values give an
averaging effect with the weighting on most likely. This is generally a good estimating
tool for the closest and moderately accurate estimates. The only drawback is all three
(opt, pess, and most likely) might not always be available.
You might also like to view...
A one time security audit revealed that employees do not have the appropriate access to system resources. The auditor is concerned with the fact that most of the accounts audited have unneeded elevated permission to sensitive resources. Which of the following was implemented to detect this issue?
A. Continuous monitoring B. Account review C. Group based privileges D. Credential management
The standard toolbar ___________________________.
a. allows the programmer to place controls on the form b. contains buttons that execute frequently used commands c. is difficult to use, since you must remember the commands d. allows the programmer to create user defined controls