Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis

Which week has the lowest resource usage?

Activity Duration Predecessor
A 5 days --
B 4 days A
C 5 days A
D 6 days B
E 6 days C, D
F 6 days E
A) Week 6
B) Week 2
C) Week 4
D) Week 3

A