Explain what is meant by "nervousness" of the MRP schedule. Provide an example. Name two tools that are particularly useful in reducing system nervousness in MRP systems

What will be an ideal response?

Nervousness is the reaction to a large number of minor changes, which may introduce instability and havoc into the purchasing and production departments. Two tools for reducing system nervousness are time fences and pegging.

Business

You might also like to view...

If the Ontario government passed a new sexual offences law. Which of the following statements best describes this law? The law

A) was validly passed pursuant to section 91 of the Constitution Act B) is ultra vires the powers of the Ontario government C) was validly passed pursuant to section 92 of the Constitution Act D) can exist along with the Criminal Code E) is only valid if all other provinces adopted a similar law

Business

Which of the following is not a type of property and liability insurance?

A) Boiler and machinery insurance B) Personal lines insurance C) Health insurance D) Commercial lines insurance

Business