Using the simplex method, we know we have an optimal solution when

A) all slack variables have a zero value.
B) all basic variables are negative.
C) all the real variables have a nonzero value.
D) all the artificial variables have a positive value.
E) None of the above

E

Business

You might also like to view...

The dimensions on which functional departments can vary include all the following EXCEPT ____ orientation.

a. time b. customer c. technological d. interpersonal

Business

Termination by addition occurs when:

A) Scope creep adds too many activities to the project that prevent it from being completed on time or within budget. B) The project is so successful that it becomes institutionalized. C) A new project is added to the organization and it commands all of the resources for the original project. D) New members join the project team once the project has begun and their skills are insufficient to successfully complete the project.