A project consists of six activities (all times are given in days). Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule

Activity Activity time Activity Cost Predecessor
K 10 140
L 8 64 K, M
M 12 96
N 6 120 M
P 14 168 L
Q 12 144 N

Highest resource usage occurs during days 21 and 22 with activities N and P requiring a combined 32 units of resources. The lowest usage of 8 resource units occurs on days 1 and 2 for activity M and days 13 through 16 with activity L.

Business

You might also like to view...

The following are the current month's balances for Adams Marketing Company

Accounts Payable $7,000 Revenue 11,000 Cash 3,000 Expenses 1,500 Furniture 14,000 Accounts Receivable 14,000 Common Stock 10,250 Notes Payable 5,500 What is the net income for Adams Marketing for the current month? A) $11,000 B) $9,500 C) $12,500 D) $14,000

Business

When a man bought a property, he was not told about the septic tank installation. The buyer's right would be to:

A: Sue the broker for disciplinary action; B: Rescind the contract; C: Demand that the seller pay for a percolation test; D: File a report with the local health department.

Business