A project has been established in a large online retailer to develop a new secure online retail platform. During the development, you discover that a key piece of software used as part of the base platform is now susceptible to recently published exploits. Who should be contacted FIRST by the project team to discuss potential changes to the platform requirements?

A. stakeholders
B. project sponsor
C. upper management
D. change control board

D
Explanation: The change control board should be contacted first to discuss the potential changes to the platform requirements. The change control board should always be contacted first when a change must be made to the project.
Next, you should contact the project stakeholders. After that, you can notify the project sponsor and upper management.

Computer Science & Information Technology

You might also like to view...

The Percent column in Resource Sheet view of Project 2013 determines the maximum percentage of capacity a resource is available to work

Indicate whether the statement is true or false

Computer Science & Information Technology

Of the four 2D collision types, which one offers the most flexibility, but at a cost to performance?

What will be an ideal response?

Computer Science & Information Technology