Complete the table; find average lateness, average completion time, and average number of jobs in the system. Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then D)
Job Process Time Flow Time Due Date Lateness
A 5 7
B 3 9
C 2 12
D 5 4
Sum (Average) 15 (3.75 ) XXXXX
Job Process Time Flow Time Due Date Lateness
A 5 5 7 0
B 3 8 9 0
C 2 10 12 0
D 5 15 4 11
Sum (Average) 15 (3.75 ) 38 (9.5 ) XXXXX 11 (2.75 )
Avg lateness = 11/4 = 2.75 days
Avg completion time = 38/4 = 9.5 days
Avg number of jobs in the system = 38/15 = 2.53 jobs
Business
You might also like to view...
________ are the largest ethnic minority group in the United States
A) African Americans B) Hispanics C) Asians D) Native Americans E) Arabs
Business
Which of the following groups of ratios primarily measure risk?
A) liquidity, activity, and profitability B) liquidity, profitability, and market C) liquidity, activity, and debt D) activity, debt, and profitability
Business