A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:

A) 7/9.
B) 7/6.
C) 1/3.
D) 2/3.

Answer: B