Gleason Construction enters into a long-term fixed price contract to build an office building for $20,000,000. In the first year of the contract Camey incurs $6,000,000 of cost and the engineers determined that the remaining costs to complete are $15,000,000. How much gross profit or loss should Gleason recognize in Year 1 assuming the use of the completed-contract method?
A) $1,000,000 loss
B) $1,000,000 profit
C) $0
D) $350,000 loss
Answer: A