List the primary steps in the request for proposal process.

What will be an ideal response?

(1). Conduct a user needs analysis.
(2). Develop a purchase specification for the equipment or software, based on the needs analysis, to describe the technical characteristics and features of the hardware or software it wants to acquire.
(3). Define the decision criteria and the importance of each criterion. Many criteria are based on mandatory or desirable product features; other criteria include technical support, vendor stability, product costs, and compatibility with existing technology.
(4). Write the RFP document, which describes the user requirements, bidding procedure, and decision criteria.
(5). Send the RFP document to prospective vendors (some organizations maintain a list of vendors who are prescreened to meet acceptable financial stability criteria).
(6). Receive written proposals from interested vendors that address how their products meet or exceed the user requirements and include a bid price at which each vendor can supply the products or services.
(7). Analyze the responses to the RFP and have the user support staff evaluate them, often using weighted point evaluation methods.
(8). Select a vendor and award the purchase contract.

Computer Science & Information Technology

You might also like to view...

In Microsoft Access 2016, the _________ is the "many" table in a one-to-many relationship. A. primary table B. secondary table C. related table D. access table

Fill in the blank(s) with the appropriate word(s).

Computer Science & Information Technology

If you want to unlink a mask to move it independently of its layer, click the ___ icon on the Layers panel

a. mask b. link c. options bar d. layers

Computer Science & Information Technology